I have already done a video answering the question ‘What is Earned Value Management (EVM)?’ And the often, most important measure in EVM is the Estimate at Completion (EAC). So, in this video, I want to answer the question, what is the Estimate at Completion?
This video is safe for viewing in the workplace.
This is learning, so, sit back and enjoy
Estimate at Completion (EAC)
The Estimate at Completion is the expected total cost of your project, when all work is completed.
So, if everything is running to budget and to schedule, your EAC is equal to your original Budget at Completion (BAC).
However, if your costs have drifted from plan, you can calculate your EAC from your Actual Cost of Work Performed (AC or ACWP) by adding to it your Estimate to Complete (ETC).
EAC = AC + ETC
Estimate to Complete (ETC)
So, how can you calculate your ETC?
If you assume that any past problems will no longer continue and that the remains of your budget estimates are sound, then you will continue according to your original plan. Your ETC is your Budget at Completion, less the Budget Cost of Work Performed (BCWP), which is your Earned Value (EV):
ETC = BAC – EV
Estimate to Complete if You Have Underperformed
If you already have a substantial underperformance, this could represent a serious or willful decision to ignore that fact. So, before you use this approach, ask: ‘what evidence do we have that things will change?’
If, instead, you assume that the past performance will continue, then you can calculate your Cost Performance Index (CPI) and use that to calculate your ETC.
CPI = EV/AC
ETC = (BAC – EV)/CPI
This approach simplifies to give:
EAC = BAC/CPI
The implicit assumption in this approach is that the CPI will continue at the same level through the remainder of your project.
Estimate to Complete if You Have Seriously Underperformed
The most sophisticated approach uses a combination of the Cost Performance Index AND the Schedule Performance Index (SPI) to calculate the Estimate to Complete:
ETC = (BAC – EV)/(CPI x SPI)
This is also the most pessimistic approach and is a reasonable one to take, if you fear additional future delays or over-runs, beyond the levels of under-performance so far.
Estimate to Complete from First Principles
But, the precision of this approach does not mean it is necessarily going to give you an accurate ETC.
In a truly uncertain environment, you may be best to assume your original plan is no longer a sound basis for estimating.
In this case, it will be best to calculate a new estimate from fresh assumptions. Most often this will be a bottom-up estimate that considers all the work items to be carried out.
So, I’ll represent this as:
ETC = ETC*
Why all this complexity, with different ways to calculate your Estimate at Completion?
Firstly, the calculation of EAC is simple:
EAC = AC + ETC
But that just moves the complexity to your Estimate to Complete. But, the answer is simple. We are talking about estimates and forecasts. They are all uncertain. And to find the best way of estimating, we need to understand the situation and select the model that best suits the evidence.
Your estimate will be wrong. Your goal is to make it as un-wrong as you possibly can.
Recommended Videos
Carefully curated video recommendations for you:
- What is Earned Value Management – EVM? | Video
- How to Estimate Project Costs | Video
- Project Cost Management and Self Preservation | Video
- How to Deliver Effective Project Cost Management | Video
- What is Sunk Cost? …and the Sunk Cost Fallacy? | Video
- Project Financial Management – 5 Tips for Good Cost Control | Video
- How to Anticipate Future Budget Challenges to Your Project | Video
- Pressure to Reduce Your Project Budget | Video
Recommended articles
- Earned Value Primer: The Basics of EVM
- 3 Ways to Produce Your Next Project Budget
- Project Estimating Skills: How to Master Successful Project Estimation
- Project Cost Management: What You Need to Know and Do
- Make Your Project Estimation More Reliable, Using the PERT Method
What Kit does a Project Manager Need?
I asked Project Managers in a couple of forums what material things you need to have, to do your job as a Project Manager. They responded magnificently. I compiled their answers into a Kit list. I added my own.
Check out the Kit a Project Manager needs
Note that the links are affiliated.
Learn Still More
For more great Project Management videos, please subscribe to the OnlinePMCourses YouTube channel.
If you want basic Management Courses – free training hosted on YouTube, with 2 new management lessons a week, check out our sister channel, Management Courses.
For more of our Project Management videos in themed collections, join our Free Academy of Project Management.
For more of our videos in themed collections, join our Free Academy of Project Management.
What is Estimate at Completion? | Video Share on X